| DPS Fequently Asked Questions
The following was sent by Gene Piermattei Jan. 3, 2011

To: All Elevator Companies
From: Department of Public Safety
Subject: FAQ
Good Morning!
What do I need to submit to obtain a permit?
If this is a new installation, a relocation or material change (as defined by 524 CMR section 15.01:(2)), you are required to submit plans signed by a registered architect or a registered professional engineer. The plans shall bear a registering stamp certifying that the registered architect or P.E. has examined the plans and found that the building structure will comply with the contract load plus its tare as they are shown on the elevator drawing.
New installation plans (layout drawings) shall also include all items (where applicable) listed in A17.1 – 2004 Section 2.28, 524 CMR Section 35:00 Part 2 Section 2.28 and Part 3 Section 3.28.1.
If you are applying for a new installation, relocation, material change and alteration/modernization permit you are required to submit plans and/or specifications in a hard copy and electronic submission (copy of the plans and/or specifications in PDF format on a CD or flash drive) for the equipment you will be installing.
No elevator shall be installed or altered until a copy of the plans and specifications of such elevator or of the proposed alterations have been filed by the owner of the premises where such elevator is to be installed or altered, or by the manufacturer of such elevator (M.G.L. Chapter 143 Section 62).
All applications not submitted properly will be returned.
Respectfully,
Gene Piermattei
Technical Code Coordinator
gene.piermattei@state.ma.us
This was not a Constant Contact email, but a direct send, if you need a copy, please email mesassoc@hotmail.com |